Estimate how long a battery can run your load.

Convert battery capacity into usable energy, account for conversion losses, and see the assumptions behind the estimate.

Battery and load

What changes real runtime?

  • Battery chemistry: lead-acid batteries are commonly kept above a deeper discharge limit, while many lithium batteries allow more usable capacity.
  • Load and temperature: high current and cold conditions can reduce available capacity.
  • System losses: inverters, converters, wiring, and idle draw consume energy too.
  • Battery condition: age, charge level, and the system cutoff voltage all affect the result.

A short lesson

Amp-hours are not the whole story

Amp-hours describe charge capacity. Multiplying amp-hours by battery voltage converts that rating to watt-hours, a more useful measure when a load is rated in watts.

A 12 V, 100 Ah battery contains a nominal 1,200 Wh. If you plan to use 50% of its capacity and an inverter is 90% efficient, about 540 Wh reaches the load. A steady 500 W load therefore has an idealized runtime of about 1 hour and 5 minutes.

Runtime estimates are planning numbers, not guarantees. Motors and compressors may also need a brief startup surge that is much higher than their running power.

Choose assumptions

Usable capacity protects the plan

Usable capacity is the share of the battery rating you intend to consume. Your battery manufacturer or system documentation should be the first source for that limit.

When a load is entered in watts, efficiency accounts for conversion between the battery and the device. When load is entered in amps, the calculator treats that as current drawn directly from the battery and does not apply a second efficiency loss.

Safety note: Confirm wire size, fusing, battery current limits, ventilation, and inverter surge capacity with manufacturer guidance or a qualified installer. Never short a battery.

Educational references: Schneider Electric battery sizing guidance and Victron Energy battery bank guidance. This estimate does not replace battery, inverter, or equipment specifications.